For many, summer includes taking a vacation, sunning by
the pool or reading a good book.
At Eastern Michigan University, the summer months are
the prime construction season on campus. And, this summer,
particularly, as barrier fencing and torn-up sidewalks
and parking lots have been the norm.
 |
CONSTRUCTION CENTER: Construction on the
west
side of Mark Jefferson — marked by the sight of huge
cranes — has been the focal point of activity on
campus this summer. The project's first phase will
create an 86,130-gross-square-foot
addition to the
existing structure. The facility
is expected to open in
fall 2010. |
"Overall, we're pretty excited here at the physical plant
with all the physical improvements taking place. We have
$175 million in construction planned over the next three
years," said Scott Storrar, EMU's director of facilities
planning and construction services. "We're encouraged that,
when all the students, faculty and staff return, there
will be a noticeable difference to facilities and campus
as a whole."
The most visible project has been the construction at
Mark Jefferson. Four large cranes (the tallest measuring
225 feet and used to erect steel) , bulldozers and dump
trucks have been familiar sights since late April on the
west side of the existing science building structure. Approximately
$90 million of the bond money is being used for this project.
Most of this summer's effort on the science complex is
site work that includes laying the foundation for the building
addition, relocation of a section of existing utilities
and creation of an underground detention system.
The project will involve a renovation and modernization
of existing space in the Mark Jefferson Building, which
was originally constructed in 1967. The project's first
phase will create an 86,130 gross square-foot addition
to the existing structure. The second phase will renovate
the existing 182,802-square-foot structure and focus on
improving mechanical and electrical systems, structural
improvements, a new roof and site improvements.
The new science complex will house biology, chemistry,
geography and geology, physics and astronomy, and psychology.
"We're slated to receive the fabricated steel for the
addition. We're going to complete the addition first before
going into renovation of the existing building," Storrar
said. "We're looking to have the structure of the addition
far enough along in November so we can be in a position
to work inside through the winter."
The goal is to open the science complex in fall 2010,
Storrar said.
Pray-Harrold planning
While movement on Mark Jefferson is visible to anyone
who has to navigate the spider web of fencing surrounding
that project, work on renovating Pray-Harrold won't start
until late January 2010 or early February 2010, Storrar
said.
But, the $42 million renovation project is progressing.
Last September, Gov. Jennifer Granholm approved $31.5 million
in capital outlay funds for Pray-Harrold, EMU's largest
— and oldest — classroom building. Eastern
Michigan is contributing $10.5 million or 25 percent of
the cost. Pray-Harrold, at 237,108 square feet, was built
in 1969 and serves an average of 10,000 students a day.
Design development documents were completed at the end
of August, Storrar said.
"We've mostly concentrated on the mechanical and electrical
infrastructure systems. We will do some renovations to
the auditoriums and create common space on the main level
and enhance the aesthetics of the main entry on the second
floor," Storrar
said.
New DPS headquarters
 |
TECHNICAL CENTER: The former Hoyt Conference
Center is the new headquarters of EMU's Department
of Public Safety, Parking, and Health and Safety.
Here, dispatcher Christine Harrison monitors multiple
computer screens in the dispatch center. |
During August, the Department of Public Safety, Parking
and Emergency Management made its long-anticipated move
into new headquarters at the former Hoyt Conference Center
on 1200 Oakwood St. A $3.9 million renovation of 12,000
square feet of office space began in January and DPS employees
moved into their new digs Aug. 10. Approximately 33 police
officers and DPS administrators made the move from the
parking structure near Bowen Field House.
"We relocated the entire dispatch unit from the parking
structure to Hoyt Conference Center," Storrar said.
"The new police building is a tremendous step up for the
police department," said Greg O'Dell, EMU's executive director
of public safety. "It's greatly improve the working conditions
of police officers. It is now customer-friendly. Rather
than having one cramped parking window, we now have four
separate window. We're ready to operate for the fall rush."
Existing space on Hoyt's main level and a portion of the
basement were renovated and a sally port, elevator and
stair tower addition were built, Storrar
said.
Additional space in Hoyt also now allows DPS to have interview
rooms for people to report crimes on campus. Previously,
there was only a small briefing room for police officers
in the previous parking structure offices. Because the
conference center is located near Hill, Hoyt and Pittman
halls, and within relatively easy walking distance from
the Student Center, it is more visible and accessible to
students on campus.
"That was one of the reasons the (Hoyt) site was
selected, its proximity to the Towers and Student Center," O'Dell
said. "I can look out my window and see that the First-Year
Center is not that far away. A recognizable location is
something we're certainly hoping for."
The main entrance is located on the northwest side of
the building. A small customer parking lot with five spaces
is now available, O'Dell said.
All phone numbers remain the same. For emergency
assistance, call 911. DPS dispatch is 487-1222. The police
administrative offices number is 487-0892. The parking
department number is 487-3450. The SEEUS phone is 487-3387.
Emergency Management's phone number is 487-0799. For
more information, go to http://www.emich.edu/publicsafety/
To hear Chief O'Dell talk about the new headquarters,
go to http://www.emich.edu/video/index.php?v=dpsnewhome
Dorm rooms continue to be upgraded
Upgrades to residence halls and campus apartments have
been staples of EMU's summer construction plan for the
past three years. This year, 23 units in Westview Apartments
are the focus of $350,000 worth of upgrades. These include
renovation of interior space, including replacement of
ceramic floor tiles, kitchen cabinets, hardwood floors,
lighting fixtures and plumbing upgrades, said Dieter Otto,
director custodial, waste management, motor pool and grounds
services.
Additionally, $265,000 has been poured into annual apartment
preparation and inspections.
"We conduct an inspection of the residence hall rooms
prior to move-in," Otto
said. "It could mean we find a light switch
is broken or a garbage disposal doesn't work.
In all, 1,586
dormitory rooms are cleaned and inspected during the summer.
Approximately 750 dorm rooms are then re-cleaned to suppport
summer camps, dining, athletics, band, etc., he said.
For Wise Hall, a major change was the replacement of the
heating system from one that is steam-based to water.
"It will allow for better individual room control and
improve energy effectiveness," Otto said.
Door alarms were installed at the First-Year Center, which
includes Walton, Putnam, Phelps and Sellers halls.
Parking process
 |
REPAVED LOT: Snow Lot was repaved this
summer
and now has 41 spaces. |
If you ask EMU employees and students what can be aggravating
about campus, parking usually is at the forefront. Or lack
of it, if you eliminate the long trudge from North Lot,
which many on campus vocally abhor.
This past summer, some new parking spaces were added and
a few existing lots completely rebuilt. The result is an
additional 29 spaces along West Circle Drive, 41 repaved
spots in the Snow Lot and 426 spaces in the Ann Street
Lot, which was torn up and rebuilt from scratch.
Sidewalk scramble
 |
NEW SIDEWALK: This sidewalk, located
between Strong and Rackham halls, was
replaced during
the summer. In all, more
than 24,730 square feet
of old sidewalk on
campus has been replaced or
new
sidewalk installed where none existed. |
If you've walked anywhere on campus this summer, it was
not unusual to come across multiple sidewalks in various
states of disrepair and marked by piled rubble. In all,
more than 24,730 square feet of old sidewalk has been replaced
or new sidewalk installed where none existed, Otto said.
This includes sidewalk replacement in front of Snow Health
Center, the Rec/IM, Sill Hall, the Coatings Research Center,
Hoyt Conference Center, Walton Hall, Putnam Hall, University
Park and the DC-1 courtyard.
New sidewalks were installed around
the retention pond on the north end of campus, and between
the volleyball and basketball courts north of the Student
Center. Concrete steps and upper and lower landings at
the Eastern Eateries were replaced, as well as one of the
steps in the DC1 courtyard.
Aesthetic enhancements
In addition to multiple construction projects, some aesthetic
enhancements took place with an emphasis on working them
into the natural landscape, Otto said.
A number of large rocks were placed near the Rec/IM, the
west entrance of the College of Business in downtown Ypsilanti,
the west side of McKenny Hall and a decorative "e" made
out of white stones was placed on the east side of Boone
Hall along Cross Street, he said.
"When school starts, you'll see all kinds of people sitting
on those rocks," Otto said. "We're replacing some of those
concrete benches."
 |
ROCK SOLID: Sisters Maria and Stella
Rodriguez
, both of Ypsilanti, take a break
and check their
text messages while
sitting on a rock bench. The
physical plant
has located a number of large rocks
around campus to serve as places for
students
to sit and relax. Maria, a
sophomore, was showing
Stella, a
freshman, the campus.
|
Retaining
walls have been replaced on the west side of Downing Hall
and at 600 W. Forest Ave. A memorial tree outside Halle
Library was replaced.
Dirt — approximately 40,000 cubic yards of it — was
excavated from the Mark Jefferson construction project
and has been used to create natural berms around campus.
"By the time we are done, we'll have excavated approximately
60,000 cubic yards. The savings by keeping the material
on campus versus sending the material to a landfill will
be approximately $800,000," Storrar said.
Some of the natural berms were built along North Lot,
North Lot 2, and Central Stores, he said.
Approximately 120 flats of flower annuals, 40 flats of
perennials and 200 yards each of topsoil and mulch were
used to spruce up various areas around campus.
Visual improvements also are taking place inside, what
with nearly 548,340 square feet of building space carpet
being cleaned; almost 302,265 square feet of floors waxed;
and more than 30,000 square feet of grouted flooring in
locker rooms and bathrooms.
"By the time the students get back, we will have either
cleaned, waxed or grouted more than 900,000 square
feet of campus flooring," Otto said.
Construction up north
 |
CREATIVE CONSTRUCTION: Approximately $2.1
million was spent to upgrade the Parsons
Project,
some of which is pictured above, near
Traverse
City. This pathway leads to a new
dining facility
(pictured) Photo by Travis Temeyer |
Not all summer construction took place on EMU's main campus.
Approximately $2.1 million was spent to upgrade the Parsons
Project near Traverse City. A nearly 3,000-square-foot
dining hall a 3,377-square-foot classroom lab/studio and
a 1,072-square-foot rustic sleeping lodge for six was built
this summer on an 86-acre wooded property in Interlochen,
near Traverse City.
"It's a retreat area with a lab studio for the arts and
sciences," Storrar said. "The construction is low impact."
Jean Noble Parsons, a renowned sculptor and potter, passed
away in 2000 and left a $2.2 million gift of cash and property
in her trust to EMU. The trust included $1.75 million in
cash and $489,000 in property.
Eastern Michigan University's departments of art, biology
and psychology currently offer numerous spring and summer
classes and workshops on the property through EMU's Continuing
Education program.
"It's definitely an exciting time for EMU," Otto said.
Odds and ends
There were a number of projects completed this summer
that don't fall into any discernible category, but nonetheless
were important. They are as follows:
- Doors were replaced and areas cleaned up on the stairwells
of the parking structure near Bowen Field House. Relighting
those stairwells with LED (light emitting lighting diode)
will take place this fall, Storrar said.
- Classroom 101 in the College of Business was renovated
at a cost of $69,000. A larger classroom was converted
into two smaller classrooms, which will utilize the space
more efficiently.
- The elevator in the Porter Building was out of commission
during May, June and part of July due to a leak in the
hydraulic jack. The elevator came back online July 15.
The cost of the project was a little more than $54,000.
"The whole hydraulic jack assembly had to be replaced," Storrar
said.
- The Brown Hall elevator also was repaired, when 200 feet
of hydraulic oil line was replaced. In addition,
all 69 elevators were manually inspected and approved
by the state of Michigan.
- Repairs were made to the roof of Starkweather Hall.
- Air-conditioning units in King Hall were repaired. Approximately
20 feet of pipe on the main chiller pipe was replaced and
covered with temporary concrete. This work is related to
air conditioning working properly in Boone, Ford, King,
Pease, Sherzer, Starkweather and Welch halls.
- The cooling tower pump on the roof of Halle Library was
rebuilt.