The schedule is set up to work within the project's
four phases.
A graphical representation of this schedule is available
here.
Phase 1 : Inventory and Analysis - March 2003 through
April 2003
-
- Initial meeting with Facilities Planning Team (FPT): early
March
-
- Review campus documents: March through mid-April
-
- Focus group interviews: March through mid-April
-
- Site visit to inventory and analyze: March through April
-
- Prepare Analysis: March through April
-
- Meeting #2 with FPT: mid-April
-
- Open Campus Meeting #1: April 16
Phase 2 : Master Planning - May 2003 through November
2003
-
- Prepare concept for access routes: throughout May
-
- Prepare preliminary master plans: May through June
-
- Meeting #3 with FPT: final week of May
-
- EMU administration / staff workshop: final week of June
-
- Develop preliminary consensus master plan: July through
August
-
- Meeting #4 with FPT: mid-July
-
- Initiate systems planning: throughout August
- Architectural review: mid-September through mid-October
- Transportation / circulation: mid-September through mid-October
- Development zones: mid-September through mid-October
- Prepare refined master plan: mid-September through mid-November
-
- Prepare capacity projections: mid-September through
mid-November
-
- Prepare final graphics and memorandum: October through
mid-October
Phase 3 : Campus Enhancements - July 2003 through November
2003
-
- Prepare preliminary design options: mid-July through
August
-
- Prepare cost opinions: throughout August
-
- Meeting #5 with FPT: early September
-
- Open campus meeting #1: September 18
-
- Prepare final enhancement plans: mid-September through
mid-November
Phase 4 : Final Documentation - September 2003 through
January 2004
-
- Prepare preliminary documents: mid-September through
November
-
- Meeting #6 with FPT: early November
-
- Prepare final documents: October through December
-
- Assemble and deliver hard copy: November through December
-
- Presentation to the Board of Regents: January 15, 2004