MARK JEFFERSON SCIENCE COMPLEX CONSTRUCTION UPDATE
April 18th, 2011 update.
The following construction related activities are scheduled to take place during the week of April 18th.
- Continue block work in the basement and 1st floor
- Installing mechanical piping in the basement, 1st and 2nd floors
- Continue ductwork installation in the basement, 1st and 2nd floors
- Working in the new electrical room on 2nd floor
- Continue drywall on the 2nd floor
- Working on in-wall rough-ins on all floors
- Continue window installation on 1st and 2nd floors
- Start painting in the basement
Note: There will be noise and vibration generated during the execution of this week's construction activity that may be sensed in Strong Hall and Mark Jefferson.
The following construction related activities are scheduled to take place during the week of April 25th.
- Continue in-wall rough-ins in the basement and on the 1st floor
- Working in the new electrical rooms
- Continue duct installation in the basement and on the 1st floor
- Working on piping installation in the basement, 1st and 2nd floors
- Continue window installation on the 1st floor
- Continue drywall on 2nd floor
- Start painting on the 2nd floor
Note:
There will be noise and vibration generated during the execution of
this week's construction activity that may be sensed in Strong Hall and
Mark Jefferson.
MARK JEFFERSON CONSTRUCTION UPDATE
Commencing with the end of classes for the Fall Semester, contractors for the
Science Complex project shall prepare the site for start of
construction activities. These activities include the relocation of
underground utilities and the addition to the west side of the existing
Mark Jefferson Science Building. Construction fencing, gates and
temporary barricades shall be placed to separate the construction area
from public parking areas and pedestrian routes. Safety, barrier free
parking, and way finding signage shall be installed as part of this
work.
Vehicle parking in the South Oakwood Lot and McKenny Guest Lot will continue with
modifications. A portion of the McKenny Guest Lot will be reserved for
contractor trailers, material lay-down, and construction deliveries.
Barrier free parking spaces will be created in the South Oakwood Lot
and McKenny Guest Lot to accommodate those areas impacted by the
construction site fencing. Pedestrian crosswalks for barrier free
access to the campus shall be identified by pavement striping.
Pedestrian access to the west side of Mark Jefferson and Strong Hall will be
impacted during the construction period. A temporary pedestrian walkway
shall be erected along the east side of the South Oakwood Lot between
parking areas and the construction fence. The ADA handicap assist
entry-door located at the northeast side of Mark Jefferson will remain
in operation. Within the Mark Jefferson building, the stairwells at the
northeast and southeast corners of the building will remain in
operation for all floors and as a means of emergency egress. The
stairwells at the northwest and southwest corners of the building will
remain in operation for all floors but not as a means of emergency
egress.
Delivery access to the west side of Mark
Jefferson and Strong Hall will be impacted during the construction
period. Temporary delivery access to both buildings will be from the
sidewalk area north of Strong Hall along West Circle Drive. The ground
floor entrance at the northwest side of Strong Hall will remain
accessible. The delivery access to Mark Jefferson shall be made via the
tunnel connecting Strong Hall.
These temporary protective measures shall be in place prior to the
commencement of the Winter 2009 semester classes. They will remain in
place until the completion of the addition.
Mark Jefferson Vehicle and Pedestrian Access Map