MARK JEFFERSON SCIENCE COMPLEX CONSTRUCTION UPDATE
All,
The following construction activity update was provided by Christman/Dumas.
The following construction related activities are scheduled to take place during the week of November 16th.
We are projecting the percentages complete through November 20th.
- Begin steel erection 17 line north 10%
- Continue south D line retaining wall 80%
- Start fireproofing in the basement mechanical room 15%
- Continue MEP coordination 10%
- Continue demolition of the core area in Mark Jefferson 50%
- Continue the mechanical cut and cap in the core area of Mark Jefferson 25%
- Begin 3rd floor west parapet formwork 25%
- Cast 4th and 5th floor slabs from 16 line south 100%
- Begin installation of the clips for the curtain wall system 2%
- Complete the below grade AA line wall 100%
- Complete the underpin of the northwest Mark Jefferson stair tower 100%
- Continue installation of temporary power distribution system and install temporary lighting.
Note: There will be noise and vibration generated during the execution of this week’s construction activity that may be sensed in Strong Hall and Mark Jefferson.
The following construction related activities are scheduled to take place during the Week of November 23rd.
We are projecting the percentages complete through November 27th.
- Continue steel erection 17 line north 25%
- Complete the sub-basement slab on grade to 22 line 100%
- Continue south D line retaining wall 100%
- Continue fireproofing in the basement mechanical room 40%
- Continue MEP coordination 10%
- Continue demolition of the core area in Mark Jefferson 60%
- Continue 3rd floor west parapet formwork 25%
- Continue installation of the clips for the curtain wall system 5%
- Mobilize the masonry contractor
- Retaining wall on AA line south of 5 line 15%
Note:
There will be noise and vibration generated during the execution of
this week's construction activity that may be sensed in Strong Hall and
Mark Jefferson.
Activities completed to date:
- New sanitary sewer installation and tie in.
- 60” storm detention system west of the addition and in the Oakwood parking lot.
- Reroute of the primary electrical loop to Mark Jefferson.
- Installation of the bypass water main.
- Existing natural gas main reroute.
- Interior underpin of the stairwell in Strong Hall.
- Tie in of new tunnel utilities – steam, condensate and compressed air.
MARK JEFFERSON CONSTRUCTION UPDATE
Commencing with the end of classes for the Fall Semester, contractors for the
Science Complex project shall prepare the site for start of
construction activities. These activities include the relocation of
underground utilities and the addition to the west side of the existing
Mark Jefferson Science Building. Construction fencing, gates and
temporary barricades shall be placed to separate the construction area
from public parking areas and pedestrian routes. Safety, barrier free
parking, and way finding signage shall be installed as part of this
work.
Vehicle parking in the South Oakwood Lot and McKenny Guest Lot will continue with
modifications. A portion of the McKenny Guest Lot will be reserved for
contractor trailers, material lay-down, and construction deliveries.
Barrier free parking spaces will be created in the South Oakwood Lot
and McKenny Guest Lot to accommodate those areas impacted by the
construction site fencing. Pedestrian crosswalks for barrier free
access to the campus shall be identified by pavement striping.
Pedestrian access to the west side of Mark Jefferson and Strong Hall will be
impacted during the construction period. A temporary pedestrian walkway
shall be erected along the east side of the South Oakwood Lot between
parking areas and the construction fence. The ADA handicap assist
entry-door located at the northeast side of Mark Jefferson will remain
in operation. Within the Mark Jefferson building, the stairwells at the
northeast and southeast corners of the building will remain in
operation for all floors and as a means of emergency egress. The
stairwells at the northwest and southwest corners of the building will
remain in operation for all floors but not as a means of emergency
egress.
Delivery access to the west side of Mark
Jefferson and Strong Hall will be impacted during the construction
period. Temporary delivery access to both buildings will be from the
sidewalk area north of Strong Hall along West Circle Drive. The ground
floor entrance at the northwest side of Strong Hall will remain
accessible. The delivery access to Mark Jefferson shall be made via the
tunnel connecting Strong Hall.
These temporary protective measures shall be in place prior to the
commencement of the Winter 2009 semester classes. They will remain in
place until the completion of the addition.
Mark Jefferson Vehicle and Pedestrian Access Map